Taylor Road Improvement Project

Taylor Road Improvement Project
Location: 25th Street to Rocky Ford Road
The City of Columbus is currently reconsidering the design for the improvement of this section of street.  This street is a suburban collector street. The City plans to hold a public meeting to discuss the proposed design of the project. The funding source for the project is 80% federal funds and 20% local (thoroughfare fund).
Construction is scheduled for 2016.
Construction is expected to last one construction season.
Project Data
Traffic Volume:
6,790 vehicles per day 2010
Future Traffic Volume:
12,260 vehicles per day 2030
Project Length:
1.00 miles
Designer:
DLZ
Estimated Construction Cost: $2,800,000

Updated March 8, 2013

 



 