As part of the 2020 City Overlay project, Milestone crews will begin repairs on Monday 8/24. They will be installing underdrain along Chapel Drive and storm sewer at the intersection of Mission Drive and Chapel Drive. Milestone will begin patching in Flatrock Park North on Tuesday and continue patching the streets below. Work for the Overlay project is a three-step process: patching, milling and paving. There may be times between stages when there will be no work activity on the streets. Please be patient, reduce speeds and use extra caution while in these work zones. Please follow construction signage, obey flag personnel and obey posted “No Parking” signs.
To see the streets effected, download the press release below.
City Overlay Press Release (PDF)
City Hall
Location
123 Washington Street
Columbus, Indiana 47201
(812) 376-2500
TDD: Call 711
Fax: (812) 376-2564
Contact Us
Hours
Monday – Friday
8:00 a.m. – 5:00 p.m.